Summary
The $604K construction management contract passed, but the project still has a roughly $7 million gap, funded through solid waste ordinance fees that haulers may pass on to residents.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed May 13, 2026.
Impact analysis
Solid waste disposal fees could rise as the county covers a multimillion-dollar shortfall.
County residents gain a modern recycling facility.
Residents and businesses may face higher disposal costs passed through by haulers.
Mentions & discussions (2)
September 22: Genesee County to Host Community Input Session on Planned Recycling and Education Center
Genesee County, MI — Genesee County will host a community input session on Tuesday, September 22, to share information and answer questions about the County’s planned Recycling and Education Center. The session will begin at 5:30 p.m. in the first-fl...
Board of County Commissioners — May 13, 2026
The $604K construction management contract passed, but the project still has a roughly $7 million gap, funded through solid waste ordinance fees that haulers may pass on to residents.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Genesee County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.